[haguruka] Rwanda: Kagame Has A $241 Million Scandal

 

Rwanda: Kagame Has A $241 Million Scandal

Kagame announced Vision 2050 in 2016

By David Himbara
President Paul Kagame likes to say that he is a highly competent chief operations officer of Rwanda Inc. The 2017 Auditor General's Report shows the reverse. CEO Kagame has an egg on his face. Delayed and abandoned projects by different government entities are costing Rwanda a fortune — US$241 Million (RWF206.8 Billion) to be exact.
An astonishing scandal
As of June 2017, the number of delayed and abandoned projects was 109. These projects are spread across government at both national and sub-national levels. Much of the US$241 Million was tied up in infrastructure, especially electricity. And much of this is donor money.
Source: REPORT OF THE AUDITOR GENERAL OF STATE FINANCES FOR THE YEAR ENDED 30 JUNE 2017

Abandoned projects
An example of abandoned projects is the construction of substations of 220 KV transmission system connecting Kibuye-Karongi-Rubavu-Goma-Kigali. The total cost of the project is US$26.9 Million (RWF 23.8 Billion). Work started in November 2013. The project was to be completed by October 2015. The project remains in shambles for years later. As the Auditor General explains,
"The audit identified that the contractor had abandoned the works. EDCL has not yet contracted another contractor to complete the abandoned works and hence no progress with construction of the substations. Completed works may start deteriorating and electricity is not being transmitted to some areas as it was envisaged due to incomplete substations."
Delayed projects
An example of delayed projects is the Centre of Excellence for Biomedical Engineering at the University of Rwanda. In December 2014, the Government of Rwanda signed a loan agreement worth US$21.2 Million with the African Development Bank for setting up the Centre. The implementation period was 5 years ending 7 December 2019. As the Auditor General states, however,
"the audit identified that the project only executed 3.41% of its budget for the year ended 30 June 2017."
The 2017 Auditor General report makes a sad reading about an astounding waste of vital projects that could improve Rwandan lives. Sadly, most of the delayed and abandoned development projects are in a sector that is already pathetic – electricity generation and transmission. The US$241 Million scandal is indictment of the Rwandan dictator as well as donors who pump these resources without accountability.

###
"Hate Cannot Drive Out Hate. Only Love Can Do That", Dr. Martin Luther King.
###

__._,_.___

Posted by: Nzi Nink <nzinink@yahoo.com>
Reply via web post Reply to sender Reply to group Start a New Topic Messages in this topic (1)

Have you tried the highest rated email app?
With 4.5 stars in iTunes, the Yahoo Mail app is the highest rated email app on the market. What are you waiting for? Now you can access all your inboxes (Gmail, Outlook, AOL and more) in one place. Never delete an email again with 1000GB of free cloud storage.


.

__,_._,___

Comments

Popular posts from this blog

[Rwanda Forum] Kigali-Kisangani: Muhoozi's bellicose tweets reignite regional tensions.

"My father, General Yoweri Museveni, told me a few months ago that I must turn the UPDF into a 'killing machine.' That is what we are working on." https://www.therwandan.com/kigali-kisangani-muhoozis-bellicose-tweets-reignite-regional-tensions/ Kigali-Kisangani: Muhoozi's bellicose tweets reignite regional tensions March 23, 2025 General Muhoozi Kainerugaba, commander of the Uganda People's Defence Forces (UPDF) and son of President Yoweri Museveni, has once again shaken the regional diplomatic and military landscape with a series of controversial tweets. These posts, shared via his X account, come just after he completed an official visit to Kigali, where he was warmly received by the Chief of Staff of the Rwanda Defence Force, General Mubarakh Muganga, and personally thanked President Paul Kagame for his hospitality. In one of his most striking tweets, Muhoozi stated: "Within a week, either the M...

[AFRICAFORUM] Tr : [hinterland1] Tr : L'OCCUPATION RWANDAISE EN MARCHE

  ----- Mail transféré ----- De : Mpania Jean <drjeanmpania@yahoo.fr> À : Hinterland <hinterland1@yahoogroupes.fr> Envoyé le : Mercredi 26 février 2014 17h13 Objet : [hinterland1] Tr : L'OCCUPATION RWANDAISE EN MARCHE   Le Mercredi 26 février 2014 9h56, congokdp <congokdp@gmail.com> a écrit : L'OCCUPATION RWANDAISE EN MARCHE :   Voici comment les institutions et tout le système de sécurité de la RDC sont sous contrôle du Rwanda et les officiels congolais infiltrés par des «hirondelles» rwandaises! L'OCCUPATION RWANDAISE EN MARCHE :  Voici comment les institutions et tout le système de sécurité de la RDC sont sous contrôle du Rwanda et les officiels congolais infiltrés par des «hirondelles» rwandaises! Le processus d'occupation de la RDC par le lobby tutsi rwandais passe par le...

[haguruka.com] Fw: *DHR* New Vision, Uganda @Gen Fred Rwigyema's untold story.

  On Sunday, 22 November 2015, 18:52, "Jean Bosco Sibomana sibomanaxyz999@gmail.com [Democracy_Human_Rights]" <Democracy_Human_Rights@yahoogroupes.fr> wrote:   Gen Fred Rwigyemas untold story By Muwonge Magembe The death of Gen. Aronda Nyakairima on September 12; eclipsed the 25th year death memorial of Maj. Gen. Fred Rwigyema which is commemorated every October. Rwigyema died strangely in October, 1990, after launching a military invasion against President Juvenal Habyarimana. Before he left for Rwanda, Rwigyema parked a coffee brown Mercedes Benz (G-Class) near the residence of then special administrator for Mbarara district, Henry Rwigyemera. Rwigyema started living in Uganda when he was only three years following his parents' relocation from Mukiranze village, Kamonyi district, Rwanda to Nshungerezi refuge camp, Ankole and Kahungye, Toro. Their relocation was motiv...